Proper wiring and earthing are critical for the reliable operation of the IAC. This includes power supply selection, zone input wiring, and reader connections.

Technical Details

Power Supply

  • Smart PSU: Recommended for battery backup and health monitoring.
  • Lock Power: A dedicated input (T11) allows lock power to be sourced from a separate supply.
  • Ancillary Power: Powered from the IAC’s LAN+, RDR+, and DET+ outputs.

Earthing & Wiring Rules

  • 0V to Earth: Ensure “0V” terminals (LAN 0V, DET-, Battery-) are NOT connected to Earth. This prevents Earth Loops and preserves surge protection.
  • Ethernet: Use only Unshielded (UTP) Ethernet cable.

Zone Input Wiring

Uses the Integriti EOL (End-of-Line) Resistor scheme.

  • Standard Scheme: 2k2 / 2k2 (Sealed = 2k2, Alarm = 4k4, Tamper = Open/Short).
  • Legacy Support: Supports 2k2 / 6k8 scheme if firmware is V3.3.4 or later.

Configuration / Programming

  • Swap Alarm and Seal: Must be set to [Y]es for Normally Open alarm contacts.
  • Override EOL: If enabled, REX/REN inputs can use Normally Open button contacts without resistors.

Troubleshooting

  • Earth Loops: Verify no connection between 0V and Earth using a multimeter on Ohms range.